Demolishing or moving a structure

Demolition of a building shall be subject to an exhaustive process that may take 2 to 3 months. In order for an application to be approved, it must be submitted to a series of committees.

PROCEDURE

  1. Approval of new construction plans by the Town Planning Department
  2. If the residence is in a PIIA (Site Planning and Architectural Integration Program) zone, the Planning Advisory Committee must approve the plans and the architectural integration of the new building into the adjacent built environment
  3. The application is then submitted to the Demolition Committee
  4. Once the Demolition Committee has made its decision, a 30-day appeal period must be respected
  5. Following the 30-day period, the Town issues the construction and demolition permits

Given the complexity of the process, please contact the Town Planning Director in order to obtain more details.